Sl. No | Name of the Initiative | Status |
---|---|---|
1 | Construction of Container Terminal - Phase I (stage-II), 330m quay length on DBFOT basis (Capacity – 11.58 MTPA) | Yet to Commence the construction activity. |
2 | Construction of IOCL Captive Jetty on Captive user basis(Capacity-3.00 MTPA) | IOCL awarded the EPC contract for Construction of Jetty on 31.01.2022. Expected commencement of construction of jetty work by March 2022. |
3 | Construction of RoRo cum General Cargo Berth-II including car parking yard (Capacity - 3.00 MTPA) | LOA issued to M/s. L&T Geostructure Pvt Ltd, Chennai on 12.11.2021 for Rs.149.36 Cr. Project Duration- 20 months. Work commenced on 03.12.2021. Work is under progress |
4 | Dredging Plan- Phase - IV (A) | DCI commenced the work from 08.07.2020. As on date dredging quantity executed is about 3.1M.Cu.M out of 4.8MCuM under Maintenance Dredging of Phase-IV(A). Due to fish breeding season from (26/4/21 to 14/6/21) and non-availability of suitable dredger since June 2021, the dredging works has been temporarily suspended. |
5 | Modification of existing Iron ore terminal to also handle coal by SIOTL on DBFOT basis(Capacity - 12.00 MTPA) | Project currently stalled. |
6 | Multi-User Liquid Terminal-II at Ennore (Capacity - 3.00 MTPA) | Concession Agreement yet to be signed by the Concessionaire. |