Status of tenders

 


  1. Development of Road Connectivity - Southern Boundary of Port's Coal/Iron Ore Stack Yard to the
      North Chennai Thermal Power Station Road.

     
Estimated Cost :  Rs.6,17,27,000/-  

      
On Due date i.e., 12.10.2009, 11 tenderers have submitted their tender. The contract was awarded to
      M/s. RS   Development & Constructions India Pvt. Ltd., Erode
for a quoted
      value of Rs.4,98,62,030/- on 17.12.2009.

--------------------------------------------------------------------------------------------------------
 
2. Development of Car Parking Area and other Appurtenant facilities near West Gate.

      Estimated Cost :  Rs.24,07,77,300/-  

      On Due date i.e., 12.10.2009, 11 tenderers have submitted their tender. The contract was awarded to
      M/s. P & C Constructions (P) Ltd, Chennai
for a quoted
      value of Rs.21,57,30,044.50 on 02.01.2010.